5                                       WATER POLLUTION

5.1                                 Introduction

5.1.1.1                     This section describes the requirements for the monitoring and audit of water quality impacts from the Project during the construction phase. No monitoring of water quality would be required during the operation phase of the STF as there would be no discharge of wastewater effluent from the on-site wastewater treatment plant.

5.1.1.2                     The water quality assessment undertaken in the EIA Study concluded that the identified water quality impacts could be minimized by implementing the recommended mitigation measures for the construction works, such as control measures on site runoff and drainage from the works areas to minimise construction run-off and to carry out proper site management and good housekeeping practices.  The EIA Report concluded that the release of PFA leachate due to the foundation construction would not be likely to accelerate.  Marine water quality monitoring was recommended during the foundation piling of the STF to confirm the assessment results.  As such, no unacceptable residual water quality impact would be expected. 

5.1.1.3                     Regular site inspections were recommended to be undertaken to inspect the construction activities and works areas and also the status on the implementation of the recommended mitigation measures.  In addition, water quality monitoring of the Tsang Kok Stream was recommended during site formation, foundation piling of the STF, and construction of the access road in order to ensure no adverse water quality impact to the stream.

5.1.1.4                     Discharges of drainage water from the works areas would be required to comply with the terms and conditions of a discharge licence, issued by EPD, under the Water Pollution Control Ordinance (WPCO).  It may be a stipulation of the WPCO licence to require the Contractor to monitor the quality / quantity of the discharge to show compliance with the conditions of the licence.  Such monitoring would not form part of the EM&A programme. 

5.2                                 Water Quality Parameters

5.2.1.1                     Dissolved oxygen (DO), turbidity, suspended solids (SS) level and pH should be monitored at designated water quality monitoring stations in the Tsang Kok Stream during the construction works.  DO, turbidity and pH should be measured in situ whereas SS should be determined by laboratory analysis.

5.2.1.2                     With regard to the potential marine water quality impact from PFA leachate, heavy metals including cadmium, chromium and aluminium, which have the greatest tendency to leach from the lagooned PFA into the seawater, should be monitored during the foundation piling.

5.2.1.3                     Other relevant data should also be recorded, including monitoring location / position, time, water depth, temperature, weather conditions and any special phenomena or work underway at the construction site.

5.2.1.4                     The proposed water quality monitoring schedule should be faxed to EPD on or before the first day of the monitoring month.  EPD should also be notified immediately for any changes in schedule by fax.  A monitoring record sheet is presented in Appendix 5.1 for reference.

5.3                                 Monitoring Equipment

5.3.1                           Dissolved Oxygen and Temperature Measuring Equipment

5.3.1.1                     The instrument should be a portable and weatherproof DO measuring instrument complete with cable and sensor, and use a DC power source.  The equipment should be capable of measuring:

l    a DO level in the range of 0 ‑ 20 mg/L and 0 ‑ 200% saturation; and

l    a temperature of 0 ‑ 45 degree Celsius.

5.3.1.2                     It should have a membrane electrode with automatic temperature compensation complete with a cable.

5.3.2                           Turbidity Measurement Instrument

5.3.2.1                     The instrument should be a portable and weatherproof turbidity-measuring instrument using a DC power source.  It should have a photoelectric sensor capable of measuring turbidity between 0 - 1000 NTU (for example, Hach model 2100P or an approved similar instrument).

5.3.3                           pH Measurement Instrument

5.3.3.1                     The instrument should consist of a potentiometer, a glass electrode, a reference electrode and a temperature-compensating device.  It should be readable to 0.1pH in a range of 0 to 14.  Standard buffer solutions of at least pH 7 and pH 10 should be used for calibration of the instrument before and after use.

5.3.4                           Sampler

5.3.4.1                     A water sampler is required.  It should comprise a transparent PVC cylinder, with a capacity of not less than 2 litres, which can be effectively sealed with latex cups at both ends.  The sampler should have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth (for example, Kahlsico Water Sampler or an approved similar instrument).

5.3.5                           Water Depth Detector

5.3.5.1                     A portable, battery-operated echo sounder should be used for the determination of water depth at each designated monitoring station.  This unit can either be hand held or affixed to the bottom of the work boat, if the same vessel is to be used throughout the monitoring programme.

5.3.6                           Sample Containers and Storage

5.3.6.1                     Water samples for SS and three heavy metals measurements should be stored in high density polythene bottles with no preservative added, packed in ice (cooled to 4°C without being frozen) and delivered to the laboratory and analysed as soon as possible after collection.  Sufficient volume of samples should be collected to achieve the detection limit stated in Section 5.4

5.3.7                           Monitoring Position Equipment

5.3.7.1                     A hand-held or boat-fixed type digital Differential Global Positioning System (DGPS) with way point bearing indication and Radio Technical Commission for maritime (RTCM) Type 16 error message ‘screen pop-up’ facilities (for real-time auto-display of error messages and DGPS corrections from the Hong Kong Hydrographic Office), or other equipment instrument of similar accuracy, should be provided and used to ensure that the water sampling locations are correct during the water quality monitoring work.

5.3.8                           Calibration of In-Situ Instruments

5.3.8.1                     The DO meter and turbidimeter should be checked and calibrated before use.  DO meter and turbidimeter should be certified by a laboratory accredited under HOKLAS or any other international accreditation scheme, and subsequently re-calibrated at three monthly intervals throughout all stages of the water quality monitoring.  Responses of sensors and electrodes should be checked with certified standard solutions before each use.  Wet bulb calibration for a DO meter should be carried out before measurement at each monitoring location.

5.3.8.2                     Sufficient stocks of spare parts should be maintained for replacements when necessary.  Backup monitoring equipment should also be made available so that monitoring can proceed uninterrupted even when some equipment is under maintenance, calibration, etc.

5.4                                 Laboratory Measurement / Analysis

5.4.1.1                     Duplicate samples from each independent sampling event are required by EPD for all parameters.  Analysis of suspended solids and heavy metals should be carried out in a HOKLAS or other international accredited laboratory.  Sufficient water samples should be collected at the monitoring stations for carrying out the laboratory determinations. The determination work should start within 24 hours after collection of the water samples.  The analyses should follow the American Public Health Association (APHA) Standard Methods for the Examination of Water and Wastewater or an equivalent method subject to the approval of EPD.  Analytical methods and detection limits for SS and heavy metals are present in Table 5.1.

Table 5.1   Analytical Methods to be applied to Water Quality Samples

Parameters

Analytical Method

Detection Limit

Suspended Solids

APHA 2540D

1 mg/L

Cadmium

APHA 20e 3111B

0.5 μg/L

Chromium

APHA 20e 3111D

1 μg/L

Aluminium

APHA 3500-Al-D

20 μg/L

 

5.4.1.2                     Additional duplicate samples may be required by EPD for inter-laboratory calibration.  Remaining samples after analysis should be kept by the laboratory for 3 months in case repeat analysis is required.  If in-house or non-standard methods are proposed, details of the method verification may also be required to submit to EPD.  In any circumstance, the sample testing should have comprehensive quality assurance and quality control programmes.  The laboratory should prepare to demonstrate the programme to DEP or his representatives when requested.

5.5                                 Monitoring Locations

5.5.1.1                     The proposed water quality monitoring stations are listed in Table 5.2 and shown in Figure 5.1.  For the stream water quality monitoring, two monitoring stations should be set in the stream course upstream of the works areas which should act as a control stations, and three impact monitoring stations should be located in Tsang Kok stream adjacent and downstream of the works areas.  In terms of the marine water quality monitoring conducted during the foundation piling, a control station should be set in the EPD marine water quality monitoring station namely DM4 and two impact monitoring stations should be located adjacent to the East Ash Lagoon in the Deep Bay WCZ.

Table 5.2   Proposed Water Quality Monitoring Stations

Station

Description

Easting

Northing

Parameters

C1

Control stations for the Tsang Kok stream water quality monitoring

810639.3

831296.8

DO, turbidity, SS, pH

C2

810461.6

831243.9

W1

Impact monitoring stations for the Tsang Kok stream

810639.3

831296.8

W2

810461.6

831243.9

W3

810323.6

831196.1

DM4

Control stations for marine water quality monitoring

809629.8

835150.8

cadmium; chromium; aluminium

M1

Marine water adjacent to the East Ash Lagoon

809915.3

831971.6

M2

809026.4

831676.8

 

5.5.1.2                     For the stream water quality monitoring, measurement should be taken at surface and bottom layers.  For the marine water monitoring stations, sampling shall be taken at three water depths, namely, 1m below water surface, mid-depth and 1m above sea bed, except at where the water depth is less than 6m, in which case the mid-depth station may be omitted.  Shall the water depth be less than 3m, only the mid-depth station will be monitored.  The status and locations of the works activities/areas may change after issuing this Manual.  If such case arises, the ET Leader should propose with justification for changes to monitoring locations or other requirements of the EM&A programme, and seek approval from the IEC and deposit the document with EPD.

5.6                                 Baseline Monitoring

5.6.1.1                     Baseline conditions in the stream course and marine water should be established and agreed with EPD prior to the commencement of construction works.  The purpose of the baseline monitoring is to establish ambient conditions prior to the commencement of the works and to demonstrate the suitability of the proposed monitoring stations.  The baseline conditions should normally be established by measuring the water quality parameters specified in Section 5.2.  The measurements should be taken at the designated monitoring stations during mid-flood and mid-ebb tides prior to the commencement of works. 

5.6.1.2                     Other relevant data should also be recorded, such as monitoring location / position, time, water depth, weather conditions and any special phenomena underway near the monitoring station.  There should not be any construction activities in the vicinity of the stations during the baseline monitoring.

5.6.1.3                     In exceptional cases when insufficient baseline monitoring data or questionable results are obtained, the ET Leader should seek approval from the IEC on an appropriate set of data to be used as baseline reference and deposit the document with EPD.

5.6.1.4                     Baseline monitoring schedule should be faxed to EPD one week prior to the commencement of baseline monitoring.

5.7                                 Impact Monitoring

5.7.1                           Stream Water Quality Monitoring

5.7.1.1                     During the course of site formation and foundation piling of the STF and construction of the access road, impact monitoring should be undertaken three days per week with sampling / measurement at the designated monitoring stations in the Tsang Kok Stream.  Upon completion of the above construction works, the monitoring exercise at the designated monitoring locations should be continued for four weeks in the same manner as the impact monitoring.

5.7.1.2                     Two consecutive measurements of DO concentration, DO saturation, turbidity and pH should be taken at the surface and bottom layers at each location.  The monitoring probes should be retrieved out of water after the first measurement and then redeployed for the second measurement.  Where the difference in value between the first and second readings of DO or turbidity is more than 25% of the value of the first reading, the reading should be discarded and further readings should be taken.  Water samples for SS measurement should be collected at the same surface and bottom layers at each location.

5.7.1.3                     The water quality monitoring schedule should be faxed to EPD on or before the first day of the monitoring month.  EPD should be notified immediately of any changes in schedule by fax.

5.7.2                           Marine Water Quality Monitoring

5.7.2.1                     During the foundation piling of the STF, impact monitoring should be undertaken three days per week with sampling / measurement at the designated monitoring stations in the Deep Bay WCZ.  Upon completion of the piling, the monitoring exercise at the designated monitoring locations should be continued for four weeks in the same manner as the impact monitoring.

5.7.2.2                     Sampling should be taken at three water depths, namely, 1m below water surface, mid-depth and 1m above sea bed, except where the water depth be less than 6m, in which case the mid-depth station may be omitted.  Shall the water depth be less than 3m, only the mid-depth station will be monitored.

5.7.2.3                     The water quality monitoring schedule should be faxed to EPD on or before the first day of the monitoring month.  EPD should be notified immediately of any changes in schedule by fax.

5.8                                 Event and Action Plan for Water Quality

5.8.1.1                     The water quality criteria, namely action and limit levels, are shown in Table 5.3.  These criteria should be applied to ensure that any deterioration of water quality is readily detected and timely action is taken to rectify the situation.  Should the monitoring results of the water quality parameters at any designated monitoring station exceed the water quality criteria, the actions in accordance with the Event and Action Plan summarized in Table 5.4 shall be carried out.

Table 5.3  Action and Limit Levels for Water Quality

Parameters

Action

Limit

DO in mg/L

(mid-depth)

£ 5 %-ile of baseline data

£ 4 mg/L

SS in mg/L (mid-depth)

≥ 95 %-ile of baseline data or 120% of control station’s SS on the same day of measurement

≥ 99 %-ile of baseline or 130% of control station's SS on the same day of measurement

Turbidity in NTU (mid-depth)

 

≥ 95 %-ile of baseline data or 120% of control station’s turbidity on the same day of measurement

≥ 99 %-ile of baseline or 130% of control station's turbidity on the same day of measurement

pH

Within the interval of 5 percentile and 95 percentile of baseline data

pH £ 6 or pH ≥ 9

Cadmium

≥ 95 %-ile of baseline data

≥ 99 %-ile of baseline

Chromium

≥ 95 %-ile of baseline data

≥ 99 %-ile of baseline

Aluminium

≥ 95 %-ile of baseline data

≥ 99 %-ile of baseline

Notes:   

1.        For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

2.        For SS and turbidity, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

 


Table 5.4                     Event and Action Plan for Water Quality

Event

ET Leader

IEC

SOR

Contractor

Action level being exceeded by one sampling day

¨     Repeat in situ measurement to confirm findings;

¨     Identify reasons for non-compliance and source(s) of impact;

¨     Inform IEC and Contractor;

¨     Check monitoring data, all plant, equipment and Contractor's working methods;

¨     Discuss mitigation measures with IEC and Contractor;

¨     Repeat measurement on next day of exceedance.

¨   Discuss with ET and Contractor on the mitigation measures;

¨   Review proposals on mitigation measures submitted by Contractor and advise the SOR accordingly;

¨   Assess the effectiveness of the implemented mitigation measures.

¨   Discuss with IEC on the proposed mitigation measures;

¨   Make agreement on the mitigation measures to be implemented.

¨   Assess the effectiveness of the implemented mitigation measures.

¨     Inform the SOR and confirm notification of the non-compliance in writing;

¨     Rectify unacceptable practice;

¨     Check all plant and equipment;

¨     Consider changes of working methods;

¨     Discuss with ET and IEC and propose mitigation measures to IEC and SOR;

¨     Implement the agreed mitigation measures.

Action level being exceeded by more than one consecutive sampling day

¨     Repeat in situ measurement to confirm findings;

¨     Identify reasons for non-compliance and source(s) of impact;

¨     Inform IEC and Contractor;

¨     Check monitoring data, all plant, equipment and Contractor's working methods;

¨     Discuss mitigation measures with IEC and Contractor;

¨     Ensure mitigation measures are implemented;

¨     Prepare to increase the monitoring frequency to daily;

¨     Repeat measurement on next day of exceedance.

¨  Discuss with ET and Contractor on the mitigation measures;

¨  Review proposals on mitigation measures submitted by Contractor and advise the SOR accordingly;

¨  Assess the effectiveness of the implemented mitigation measures.

¨   Discuss with IEC on the proposed mitigation measures;

¨   Make agreement on the mitigation measures to be implemented;

¨   Assess the effectiveness of the implemented mitigation measures.

¨     Inform the SOR and confirm notification of the non-compliance in writing;

¨     Rectify unacceptable practice;

¨     Check all plant and equipment; Consider changes of working methods;

¨     Discuss with ET and IEC and propose mitigation measures to IEC and SOR within three working days;

¨     Implement the agreed mitigation measures.

Limit level being exceeded by one sampling day

¨     Repeat in situ measurement to confirm findings;

¨     Identify reasons for non-compliance and source(s) of impact;

¨     Inform IEC Contractor and EPD;

¨     Check monitoring data, all plant, equipment and Contractor's working methods;

¨     Discuss mitigation measures with IEC, SOR and Contractor;

¨     Ensure mitigation measures are implemented;

¨     Increase the monitoring frequency to daily until no exceedance of Limit level.

¨   Discuss with ET and Contractor on the mitigation measures;

¨   Review proposals on mitigation measures submitted by Contractor and advise the SOR accordingly;

¨   Assess the effectiveness of the implemented mitigation measures.

¨   Discuss with IEC, ET and Contractor on the proposed mitigation measures;

¨   Request Contractor to critically review the working methods;

¨   Make agreement on the mitigation measures to be implemented;

¨   Assess the effectiveness of the implemented mitigation measures.

¨     Inform the SOR and confirm notification of the non-compliance in writing;

¨     Rectify unacceptable practice;

¨     Check all plant and equipment;

¨     Consider changes of working methods;

¨     Discuss with ET, IEC and SOR and propose mitigation measures to IEC and SOR within three working days;

¨     Implement the agreed mitigation measures.

Limit level being exceeded by more than one consecutive sampling day

¨     Repeat in situ measurement to confirm findings;

¨     Identify reasons for non-compliance and source(s) of impact;

¨     Inform IEC Contractor and EPD;

¨     Check monitoring data, all plant, equipment and Contractor's working methods;

¨     Discuss mitigation measures with IEC, SOR and Contractor;

¨     Ensure mitigation measures are implemented;

¨     Increase the monitoring frequency to daily until no exceedance of Limit level for two consecutive days.

¨   Discuss with ET and Contractor on the mitigation measures;

¨   Review proposals on mitigation measures submitted by Contractor and advise the SOR accordingly;

¨   Assess the effectiveness of the implemented mitigation measures.

¨   Discuss with IEC, ET and Contractor on the proposed mitigation measures;

¨   Request Contractor to critically review the working methods;

¨   Make agreement on the mitigation measures to be implemented;

¨   Assess the effectiveness of the implemented mitigation measures;

¨   Consider and instruct, if necessary, the Contractor to slow down or to stop all or part of the construction activities until no exceedance of Limit level.

¨     Inform the SOR and confirm notification of the non-compliance in writing;

¨     Rectify unacceptable practice;

¨     Check all plant and equipment;

¨     Consider changes of working methods;

¨     Discuss with ET, IEC and SOR and propose mitigation measures to IEC and SOR within three working days;

¨     Implement the agreed mitigation measures;

¨     As directed by the SOR, to slow down or to stop all or part of the construction activities.


5.9                                 Mitigation Measures

5.9.1                           Introduction

5.9.1.1                     Mitigation measures recommended for the construction and operation phases of the Project are summarized below.

5.9.2                           Construction Phase

Construction Site Run-off and Drainage

5.9.2.1                     The site practices outlined in ProPECC PN 1/94 “Construction Site Drainage” should be followed as far as practicable in order to minimise surface runoff and the chance of erosion.  These practices include the following items:-

l              At the start of site establishment, internal drainage works and erosion and sedimentation control facilities should be implemented.  Channels, earth bunds or sand bag barriers should be provided on site to direct stormwater to silt removal facilities.  The detailed design and installation of the temporary on-site drainage system should be undertaken by the contractor prior to the commencement of construction. 

l              Before commencing any site formation work, all sewer and drainage connections should be sealed to prevent debris, soil, sand etc. from entering public sewers/drains.

l              Boundaries of earthworks should be surrounded by dykes or embankments for flood protection, as necessary. 

l              Sand/silt removal facilities such as sand traps, silt traps and sediment basins should be provided to remove sand/silt particles from runoff to meet the standards of the Technical Memorandum under the Water Pollution Control Ordinance.  The design of silt removal facilities should be based on the guidelines provided in ProPECC PN 1/94.  All drainage facilities and erosion and sediment control structures should be inspected monthly and maintained to ensure proper and efficient operation at all times and particularly during rainstorms. 

l              Water pumped out from foundation piles must be discharged into silt removal facilities.

l              During rainstorms, exposed slope/soil surfaces should be covered by a tarpaulin or other means, as far as practicable.  Other measures that need to be implemented before, during and after rainstorms are summarized in ProPECC PN 1/94.

l              Exposed soil areas should be minimized to reduce potential for increased siltation and contamination of runoff.

l              Earthwork final surfaces should be well compacted and subsequent permanent work or surface protection should be immediately performed.

l              Open stockpiles of construction materials or construction wastes on-site should be covered with tarpaulin or similar fabric during rainstorms.

l              All vehicles should be cleaned before leaving the works area to ensure no earth, mud and debris is deposited on roads.  An adequately designed and sited wheel washing bay should be provided at every site exit.  The wheel washing facility should be designed to minimize the intake of surface water (rainwater).  Wash-water should have sand and silt settled out and removed at least on a weekly basis to ensure the continued efficiency of the process.

General Construction Activities

5.9.2.2                     Debris and refuse generated on-site should be collected, handled and disposed of properly to avoid entering the nearby water bodies and public drainage system.  Stockpiles of cement and other construction materials should be kept covered when not being used. 

5.9.2.3                     Oils and fuels should only be used and stored in designated areas which have pollution prevention facilities.  To prevent spillage of fuels and solvents to nearby water bodies and public drains, all fuel tanks and storage areas should be provided with locks and be sited on sealed areas, within bunds of a capacity equal to 110% of the storage capacity of the largest tank.  The bund should be drained of rainwater after a rain event.

Sewage from Construction Workforce

5.9.2.4                     Temporary sanitary facilities, such as portable chemical toilets, should be employed on-site where necessary to handle sewage from the workforce.  A licensed contractor would be responsible for appropriate disposal and maintenance of these facilities.

Release of PFA Leachate from Ash Lagoon into the Aquatic Environment

5.9.2.5                     The past monitoring data showed that the water quality at the location outside the Tsang Tsui Ash Lagoons was not affected by the PFA filling operation.  Although no liner system is installed at the base of the lagoons, the low permeability values of the marine deposits and alluvium underneath the PFA layer would limit the seepage of PFA leachate.  The foundation construction of the STF is not likely to accelerate the release of PFA leachate through the base of the lagoon site.  Marine water quality monitoring is recommended during the foundation piling of the STF to confirm the assessment results.

5.9.3                           Operation Phase

Receiving Area in the STF

5.9.3.1                     An adequate number of drains should be provided at the receiving area of the STF with drain piping for draining and cleaning all areas of the floor.  The floors should be adequately sloped to floor drains for collection of drainage water during cleaning.  Such floor drains should contain no traps.  The drainage water should be routed to an outdoor vented and trapped manhole for connection to the on-site wastewater treatment plant.

Wash Down Facilities at STF

5.9.3.2                     Frequent and sufficient maintenance should be provided for the drainage system, and multiple outlets in the drainage system should be designed and provided to reduce the likelihood of drainage blockage. 

Temporary Sludge Storage at STF

5.9.3.3                     A detection device/alarm should be installed to prevent overfilling of temporary sludge storage tank.